Yesterday, the tile guy came and put in the last couple of tiles in the spa and attached the granite spillover slab. No other progress to report.
PB just texted me this morning and the electrician comes around noon tomorrow and the PebbleTec will be shot on Friday. He's going to try to get me to see a real, live Blue Lagoon pool tomorrow.
We start filling right after the PebbleTec guys are done, so this weekend is going to be tricky. The PB is thinking that it's going to take about 2 days to fill.
Matt will be out for the weekend on the MS150 bike ride and the boys and I have a regatta in Sarasota. Hopefully my mom can keep an eye out on the filling progress.
The PB will give us a form to give to the city for a sewer credit. Normally we pay for the water that comes in and the sewer that goes out, but with this form at least we don't have to pay the sewer for all that water. No idea how much this will save us but we'll take it.
The paver guys came out yesterday and fixed the neighbor's paver walkway that got cracked up by the heavy equipment. No idea how that bill will be resolved, but that's Matt's department.
Noticed that more front yard sprinklers aren't working right, so I get to do more sprinkler maintenance today. Ugh. I am so sick of fixing sprinklers.
No comments:
Post a Comment